Project timeline example
Let’s consider an example of a project timeline using a Gantt chart. In this example, we’ll outline the tasks and milestones for creating a new website. The timeline will span over four weeks.
Project: New Website Development
- Define Project Scope and Objectives: The first step is defining the purpose and scope of the new website and next is understanding the available budget and internal resources. The latter demands a detailed goal statement and a direction for the entire development. The crucial issue in this context is to list out what functionalities and features the website must possess. This serves as a significant step in the process in that it defines the goals of the project and offers guidelines to be followed in planning and implementation.
- Identify Tasks and Activities: The second phase starts with the establishment of the goals of the project, before which, the targeted tasks and activities should be identified to achieve project goals. A web designer must employ several steps as part of the process. These steps begin with doing market research to establish user needs and preferences, coming up with elaborated website requirements after the research, constructing a wireframe to show how a website will be structured, designing the user interface, writing the website code, conducting exhaustive testing and launching the completed website.
- Sequence Activities: Plan your activities with a sequence in mind which is deciding the logical order in which tasks should be performed. Here, for example, market research and a definition of the website’s requirements may stand as a base for further work. For example, developing graphic designs takes the requirements as input and the user interface is defined upon the wireframe completion. The implementation strategy follows this sequential order to ensure that the entire phase of the project is run in a structured and orderly manner.
- Estimate Duration: Synchronizing the anticipation of the timing of every task is one of the key elements in having a precise timeline. Budgeting activity time, for example, market research time frame is 1 week, is communication assistant for project planning and predicting resource requirements for activities. These frameworks can be built from historical data, experience or an industry standard. The phases should be scheduled to ensure that each one is completed within the designated time frame, so the project remains on track.
- Assign Resources: Resource allocation has to be one of the key issues to handle properly when you treat project management as absolutely effective. The marketing department handles market research while the business analyst may collect requirements for the website. UI/UX designers would be handling wireframes and design, but the development team would rather be occupied with programming. Dealing with suitable resources avoids constructing structures that are directed by incompetent individuals hence efficiency is increased and it also ensures quality.
- Create Gantt Chart:
- | Task | Duration | Start Date | End Date |
|———————–|——— -|————- |————-|
| Market research | 1 week | 2024-03-01 | 2024-03-07 |
| Define requirements | 1 week | 2024-03-08 | 2024-03-14 |
| Create wireframes | 2 weeks | 2024-03-15 | 2024-03-28 |
| Design user interface | 2 weeks | 2024-03-29 | 2024-04-11 |
| Develop website code | 3 weeks | 2024-04-12 | 2024-05-02 |
| Perform testing | 1 week | 2024-05-03 | 2024-05-09 |
| Launch website | 1 day | 2024-05-10 | 2024-05-10 | - The figure above enables the observation of the period when the task begins and ends, allowing the viewer the overall picture of the whole project and its connections. The Gantt chart not only improves internal communications but promotes collaboration among the team to build a mutual conception of the project timelines.
- | Task | Duration | Start Date | End Date |
- Set Milestones: Milestones make major achievements along the way in the project plan. In the case of creating a site, for instance, milestones could be reached after carrying out market research, completing website design requirements, creating wireframes, wrapping up interface designing, completing coding, performing website testing and finally launching the website. These benchmarks provide clear pointers for the realization of key milestones, keeping the teams focused and on course throughout the project.
Steps to Build a Project Management Timeline
The timeline needs to be one of the main focus areas of project planning and management and it should be a roadmap to help keep the teams on track and organized. In this timeline, not only is the task listed but also the dependencies are outlined and the time duration is given for each of the tasks. In this article, we shall draw a roadmap on how to make a full step-by-step project management schedule to sustain a project in the time allocated.
Table of Content
- What is a Project Timeline?
- Explain in detail all the steps of the project timeline
- Types of project timelines
- Project timeline example
- Conclusion: Project Management Timeline
- FAQs: Project Management Timeline
Contact Us