EAC Formulas and Techniques
1. EAC = AC + ETC (Estimate to Complete)
This rule refers to the case where the cost-efficiency of the past will be reflected in the coming years. It is determined by bringing the AC, ETC together to get the Actual Cost of Actual Cost (AC) Estimate to Complete (ETC)
2. EAC = BAC / CPI (Cost Performance Index)
Hence this metric is focused on the project expenditures that occurred previously. The Cost Performance Index (CPI) represents the relationship between the Earned Value (EV) and the Actual Cost (AC), which is the quotient of the EV and AC. From the perspective of calculus, EAC is the Budget at Completion (BAC) divided by the CPI.
3. EAC = AC + (BAC – EV)
This formula comprises the resulting value of the performance of the project with the actual earned one. For EAC, it takes the AC and adds the difference between the BAC and EV.
4. EAC = AC + (BAC – EV) / (CPI * SPI)
It is a formula that does not depend only on either time or expenditure but considers both. It applies CPI and SPI indexes, which stand for the Cost Performance Index and the Schedule Performance Index.
5. EAC = AC + Bottom-Up ETC
ETC is obtained by re-assessing the entire job with specific items in mind while taking into account emerging details and possible scope or condition changes. The EAC finally is calculated with the AC Combined with the ETC Baseure.
6. EAC = Revised Budget at Completion (BAC)
In case a huge change in the implementation process occurs, or the conditions of the project become different, the project manager may revise the budget plan from where the process started at the end.
What Is Estimate at Completion in Project Management (EAC)?
Estimate at Completion (EAC) is a crucial concept in project management, providing project managers with a forecasted total cost based on current performance and expenditures. By evaluating actual costs and estimating remaining expenses, EAC helps project teams anticipate the financial requirements for successful project completion. The utilization of various calculation methods adds flexibility to adapt projections as projects evolve, enhancing the precision of cost predictions.
Table of Content
- What is the Estimate at Completion in Project Management (EAC)?
- Importance of Estimate at Completion (EAC)
- Methods for Calculating EAC
- EAC Formulas and Techniques
- Example Problems
- Factors Influencing EAC Accuracy
- Real-world Applications and Case Studies
- Limitations and Challenges of EAC
- Best Practices for Using EAC in Project Management
- Conclusion: Estimate at Completion in Project Management
Contact Us